'Extraordinary blowout': New bridge cost soars $53m in a decade

'Extraordinary blowout': New bridge cost soars $53m in a decade

Thu, 19th Nov 2026 (Today)
JORDAN SMITH Local Democracy Reporter

A decade wait for a replacement bridge and intersection in a flood prone Coromandel spot has seen the cost balloon 440% from $12m to $65m in a stark illustration of runaway construction costs for delayed infrastructure.

The public will pick up more than $50m in extra costs, despite a Minister allocating funds to the job in 2016, as the long lead-in time saw estimates leap due to covid-driven inflation.

The price for a replacement Kirikiri Stream Bridge and nearby state highway intersection construction is part of work on multiple sites across the peninsula's State Highway 26 under resilience improvements.

NZTA is now "refining the scope, including reviewing the previously applied scope to identify the best value-for-money solution within the available funding," the organisation told Local Democracy Reporting

Budget 26 allocated $85 million for the network's improvements, with $65 million of that going to constructing a brand new Kirikiri Stream Bridge on State Highway 26.

The bridge and parts of SH26 will be raised three-to-four metres to provide clearance for floodwater and debris, with the nearby SH26/SH25A intersection also to be rebuilt, NZTA regional manager, infrastructure development and delivery Roger Brady told Local Democracy Reporting.

Ten years earlier, then transport minister Simon Bridges announced a mere $12 million for the project, which also included the replacement, the realigning and an upgraded intersection.

"The Government has approved funding for a $12 million project that involves replacing the bridge and realigning the state highway around the structure," Bridges said in 2016.

Asked if the rising price was an indication the project should have been completed sooner, Brady said it has been in development for several years, and therefore "current funding allocation is not directly comparable with earlier estimates".

"Those estimates pre-date COVID-19 and the significant rise in construction costs since then, particularly for labour, steel and other materials," he said.

The project was market-tested again in 2023 according to Brady, where a construction tender price was approximately $35 million, with total funding requirements clocking in at $47 million.

"The $65 million included in Budget 2026 reflects that market-tested position, with contingency and escalation applied for project risk and the time elapsed since then," Brady said.

Former Thames-Coromandel District Council mayor Len Salt has been vocal on the issue, quoting the old adage that "it'll never be cheaper than it is today".

He described the jump as "quite an extraordinary blowout", adding it raises serious questions as it affects the budget available for other roading projects across the Waikato.

"What I'd be asking them (NZTA) is 'what level of confidence do you have that you can get the job done for $65 million without costs over and above that figure'," he said.

The remaining $20 million will see work progressed at Manaia River and Owera bridges between March and July 2027, subject to detailed design, being completed.

A further four locations have been identified at Whenuakite, Waikawau, Te Kouma Hill and Whangapoua Hill, with up to 5 additional sites currently being prioritised. Work across these locations will be staged over the next 4 years.

Current Thames-Coromandel District Council mayor Peter Revell previously said he was "absolutely delighted" at the funding's announcement.

"The resilience of the network is a concern to everybody on the peninsula partly because communities get cut off... but also economically for tourists to have the confidence when they come to the peninsula they can get on and off and they're not going to be killed," Revell said.

Further long-term Crown funding will see nine sites have work delivered between March and July 2027. Locations include underslip and rockfall protection work on SH25 Thames Coast Road between Ruamahunga and Tapu, and near Whakatete and Kereta, as well as underslip treatment on SH2 in the Karangahake Gorge near Waikino.

"The SH26 Kirikiri Stream Bridge replacement will help reduce the risk of future disruption on a critical transport route for local communities, businesses and visitors," Brady said.

"While these improvements cannot remove every risk or prevent all future disruption, they will reduce the risk at priority locations and help make state highway connections around the Coromandel better able to withstand severe weather."