'Something real': Construction starts on small town's $70m flood protection project

'Something real': Construction starts on small town's $70m flood protection project

Wed, 18th Nov 2026 (Today)
LINDA HALL Local Democracy Reporter

Nearly 40 years after Cyclone Bola exposed Wairoa's vulnerability to flooding, construction is finally beginning on a $70 million flood project to protect hundreds of properties affected by Cyclone Gabrielle.

The main construction phase of the North Clyde floodway has began following a karakia at Takitimu Marae on Monday, marking a major milestone for the community.

Wairoa Mayor Craig Little said seeing machinery on the ground and the floodway taking shape gave people something real to hold on to.

"Our people have lived with uncertainty and rain anxiety for far too long. Every heavy rain warning brings it all back," Little said.

The floodway was developed following Cyclone Gabrielle, which inundated North Clyde in 2023, and further flooding in June 2024. Crown manager Lawrence Yule was appointed in August 2024 to work with the regional and district councils on a solution.

The 1.1km-long,190m-wide floodway is the centrepiece of the Crown-funded project and the largest infrastructure investment Wairoa has seen in decades.

Once complete, it will protect 586 North Clyde properties, which received Category 2C classifications following Cyclone Gabrielle, with protection against a flood with a 1% chance of occurring in any given year.

Yule said the milestone was an opportunity to recognise what the community had been through, particularly whānau still living under Category 2C classifications.

"More than three and a half years after Cyclone Gabrielle, we're now building the protection this community has been waiting for. I don't underestimate what this journey has asked of people, particularly the whānau who are still living under Category 2C and have had their lives on hold for some time," Yule said.

"I also want to thank mana whenua, including Takitimu, Ruataniwha and Tawhiti a Maru Marae and Tātau Tātau o Te Wairoa, whose guidance has shaped this project from the beginning, and the wider Wairoa community for their patience, honesty and resilience through every step of this process," Yule said.

He said the floodway was one part of a wider, whole-of-catchment approach to flood resilience for Wairoa.

"Investigations are continuing into a possible river mouth training groyne, which is a separate workstream and is not yet funded. Modelling of the upper catchment is due by the end of the year," he said.

Hawke's Bay Regional Council chair Sophie Siers said the milestone reflects what can be achieved when central government, local government, mana whenua and the community worked towards a shared goal.

"Wairoa has been waiting for this for nearly 40 years, since Cyclone Bola showed just how vulnerable the town was to flooding," Siers said.

She said it felt like much more than the start of a construction project.

"It is the point where decades of plans and promises finally become something real."

Contractors had been working on site since early 2026, first clearing trees before moving on to preparation work in August. That has included demolishing structures, preparing the site and building a temporary road between Waihirere Rd and Ruataniwha Rd, across land provided by Tātau Tātau o Te Wairoa.

The first stage of main construction will focus on the town-side stopbank area, along with project-related stormwater and drainage works.

Cultural monitors from local marae will be on site throughout, and all contractors will complete a cultural, archaeological, ecological and environmental induction this week. Main construction is expected to be completed in late 2027.

Little thanked those who made their land available and acknowledged Yule and the project team for keeping the project moving through some very challenging times.

"Now it's about getting on with the getting on and building a safer future for Wairoa."